
Berk Demir
Underground engineer specialized in tunnels, structural design and geotechnical engineering.
M: +45 60 25 49 01
E: bdberkdemir@gmail.com
W: berkdemir.github.io / LinkedIn
A: Copenhagen, Denmark
Brief Summary
I started my career as a geotechnical engineer and worked on many aspects of geotechnics such as deep excavations, deep foundations, liquefaction remediation and so on. Later, I continued my work on the Istanbul metro as lead tunnel designer for both TBM and NATM tunnels. After moving to Denmark, I continued to work on various underground projects with an increasing focus on structural design.
Professional Experience
| Period | Role | Company | Location |
|---|---|---|---|
| 2023 – Present | Senior Tunnel Engineer | COWI | Copenhagen, Denmark |
| 2021 – 2023 | Senior Tunnel Engineer | Niras A/S | Copenhagen, Denmark |
| 2018 – 2021 | Senior Geotechnical and Tunnel Engineer | Tekfen Engineering | Istanbul, Turkey |
| 2017 – 2018 | Geotechnical Design Engineer | Destech Consultancy | Izmir, Turkey & Tanzania |
| 2015 – 2017 | Geotechnical Design Engineer | Kilci Engineering | Ankara, Turkey |
| 2014 – 2015 | Technical Office Engineer | Sonar Drilling | Ankara, Turkey |
Academic Background
| Degree | University | Field | Years |
|---|---|---|---|
| MSc | Middle East Technical University, Turkey | Geotechnical Engineering | 2014–2019 |
| BSc | Middle East Technical University, Turkey | Civil Engineering | 2009–2014 |
Technical Publications
- Demir, B., Bauduin, C., Palaiologou, M., Christensen, J. D., Yding, S., & Tomac, S. K. (2024). Site tests on retaining systems and uplift anchors of Nordhavnstunnel in Denmark. In Geotechnical Engineering Challenges to Meet Current and Emerging Needs of Society (pp. 2235-2240). CRC Press. PDF
- Recommendations for Pseudo-Static Deformation for Seismic Analyses of Tunnels, Berk Demir & Pinar Akdogan Demir, 2022. Post
- Master Thesis: Performance of Short Anchors Inside the Failure Wedge (2019)
- Comparison of Simplified Piled Raft Calculation Methods with Plaxis 3D and Details of Hardening Soil Model (2019) — ResearchGate
- P-Y Curves and Turkish Building Earthquake Code Requirements (2 papers), B. Demir, A. S. Peker, S. K. Tomaç, 4th Bridges and Viaducts Symposium, 2019 — Part 1 / Part 2
- Comparison of Construction Methods of Jet Grout Columns, B. Demir, M. S. Nalçakan, 16th National Conference on Soil Mechanics and Geotechnical Engineering, Erzurum, Turkey, 2016
Skills
Software: Plaxis 2D & 3D · Python · Lusas · Strusoft FemDesign · Rocscience (Settle, Slide, RS2) · Ensoft (LPile, Group, Shaft) · Geologismiki · Optum · Autodesk Robot · Grasshopper
Python tools built in Streamlit for daily design work: RC Beam Design · Tunnel Analytical Lining Forces · Tunnel Deformation Assessment · M-N Interaction Curve · Hoek Brown Analysis · Convergence Confinement Method · Drawdown due to Tunnel · Steel Strut Capacity · Tunnel Relaxation Factor · Tunnel Face Stability · 3D Settlement Analysis · Longitudinal Pipe Capacity · Steel Fibre Crack Width · Volume Loss Fit for Measurements
Languages: Turkish (native) · English (fluent) · Danish (intermediate)
Recent Key Projects
Copenhagen M5 Metro (2023–2025)
JV: COWI & Arup | Client: Metroselskabet A/S, Denmark | Hours: >2500
Design of the M5 Metro reference design for the tender for Metroselskabet. M5 Metro is the next metro line in Copenhagen, Denmark.
Phase-1 — Innovation studies:
- Removal of lining wall in metro stations and use of retaining walls as the main lining wall
- Geopolymer concrete use in the M5 metro
- Minimum reinforcement methodology — update on the Danish square root formula
Phase-2:
- Station lead — coordination of all disciplines for the design of two underground stations, including ARC and M&E
- Structural design lead for the two underground stations (Sofistik for the main station, FemDesign for smaller structures)

Nordhavnstunnel (2022–2023)
JV: MT Højgaard & Besix | Client: Vejdirektoratet, Denmark | Hours: >800
Nordhavnstunnel is a 1.6 km cut-and-cover, cast-in-situ tunnel in Copenhagen, Denmark.
- All design works during the tender: Lusas models of representative sections, reinforcement calculations and quantity take-off, uplift anchor calculations for all segments, settlement calculations and shear key discussions
- Design coordination after the tender: design lead for structural and fire design, relationship to 3rd party, coordination of design works and QA of design reports

Valby Cloudburst Tunnel (2021–2023)
Client: HOFOR | Hours: >1300
Detailed design of 4 shafts (~15 m diameter, ~20 m depth) and DN3400/OD4000 pipe jacking.
- TBM-related studies, pipe and alignment studies
- Settlement analyses due to tunnelling and excavations
- Technical coordination of structural and geotechnical shaft design

Kransen Culvert Deep Excavation (2021–2022)
JV: Acciona & Implenia | Client: Bane Nor, Norway | Hours: 800
Design of excavation for the Sandbukta–Moss–Såstad (SMS2A) project, Kransen culvert section, using diaphragm walls and prestressed struts in a quick clay slope.
- Design lead for all temporary works, including design basis and safety discussions
- All finite element analyses including detailed temperature studies of structural elements
Design activities have been paused due to risks in the area.

GFRP Reinforcement in TBM Tunnel Segments (2023)
Client: Metroselskabet, Copenhagen | Hours: 200
As part of Metroselskabet’s innovation study initiative, the feasibility of GFRP reinforcement for TBM tunnel segments was investigated — including detailed CO₂ comparisons, fire behaviour discussions, durability studies for possible TBM tunnel depths, and load scenarios using Lusas.

Istanbul Metro / Çekmeköy–Sultanbeyli Line (2019–2021)
JV: Doğuş & Yapı Merkezi & Özaltın | Client: Istanbul Municipality | Hours: >2500
Detailed design of TBM and NATM tunnels issued to 3rd party and client review, including construction details, 2D and 3D NATM/TBM models and seismic assessments.
- TBM design: EPB TBM with 6.57 m diameter. Design packages include segment design and EPB pressure estimates for alignment. Construction details such as thrust frame, thrust ring inside NATM and launching/receiving schemes were successfully delivered.
- NATM design: Temporary support design of all NATM tunnels (including very soft soil conditions) was delivered. Coordinated, supported and QA’d the structural teams for the permanent lining design.

Other Projects
- Klimatilpasning af det centrale Lyngby (2021–2022) — 9 pipe jacking drives (DN1200) and 12 shafts in Lyngby
- Çanakkale 1915 Bridge (2018–2019) — Peer review of design including anchor block foundations, deep foundations in liquefiable areas and technical specifications
- Bodrum Highway Tunnels (2018–2019) — 2-lane NATM highway tunnels in mountainous terrain
- Akyazi–Dokurcun Road (2018) — Balanced cantilever viaduct foundation and 40 m excavation in weathered rock
- Dar es Salaam–Morogoro Railway (2018) — Geotechnical designer for 205 km design-and-build project, Tanzania
- Cargo Building Foundation, Istanbul New Airport (2018) — Turkish Airlines
- Excavation Design in Galataport, Istanbul (2017) — Salipazari Port Management
- Grand Canyon Sofia (2017) — Remediation of problematic diaphragm wall panels
- Çanakkale Children’s Science Museum (2017) — Liquefaction remediation near Aegean Sea
- Hopa–Borçka Highway Cutting (2017)
- Dam Landslide (1.5 km × 0.6 km) Stabilization (2017) — Kalehan Energy
- Polatlı–Afyon High Speed Train (2015–2017) — 88 km stretch, 57 embankments, stone columns, 40+ structures
- Ataköy Sea Pearl (2015–2017) — Retaining systems near Marmara Sea
- Ulus Cultural and Convention Center (2016–2017) — Deep excavation up to 22 m in variable ground
- Çukurova Regional Airport (2016) — Ground improvement of various buildings
- Mavişehir Optimum Mall (2016) — Deep excavation with diaphragm wall, anchor systems and jet grout foundations
- Dalaman Airport International Arrivals (2016) — Jet grout improvement for very soft clay and liquefiable sands
- Turkmenistan Gas to Gasoline (GTG) (2015–2016) — Plaxis 2D analyses and ground improvement design to reduce settlements to structural limits
- Melen Dam Road Landslide Stabilization (2015) — Stabilization of 3 million m³ landslide with heel fill
- Buski East Waste Water Treatment Facility (2015) — Jet grout ground improvement to prevent liquefaction and excessive settlements
- Technical Office support (2014–2015) — Ozdilek Mall, Riyadh Metro Line 3, Balkupu silo foundations, various deep excavation projects